Diem completed the Enerjisa Production Kozan Social Facility project in Adana in July 2022, which started in August 2021. With an area of 2,400 square meters, the project was designed by Abba Architecture, while the rough construction works, finishing works and landscape applications were carried out by Diem. The project was managed by Enerjisa Üretim's own construction department.
Enerjisa Üretim Kozan Social Facility has been planned as a mixed project for the teams of Enerjisa who inspects all power plants in Adana and its surroundings. The aim was to meet the accommodation and social space needs of Enerjisa employees.
There are gym and seminar hall for training in the basement of the project.
There is a cafeteria and game room on the ground floor of the project.
There are 11 hotel rooms for accommodation on the 1st floor of the project.
In its garden, there is an open area of the cafeteria and a playground.
On the second floor, there is a terrace area.
Diem also took part in different projects of the Sabancı Group.
Sabancı Group, founded in 1967, is one of the leading companies in Turkey, serving more than 40 million customers as of 2020, with approximately 60 thousand employees in 14 countries.
While the 5,500 square meters LEED Gold certified Enerjisa Üretim Head Office, located in Istanbul Ataşehir in July 2020, was designed by Abba Architecture, its construction works were carried out by Diem. The project had completed in an ambitious 90 days and moved.
As Enerjisa was satisfied with the process in terms of time and quality in the head office project, Diem preferred the Adana project. In addition, Diem completed the Akçansa project at Palladium Tower in 2019 and is currently implementing the Sabancı Center office floors.
Enerjisa Üretim Kozan Social Facility aims to obtain LEED Silver certificate.
With the guidance of Enerjisa's LEED consultant for the LEED Silver certificate, which was targeted at the beginning, sustainable choices were made and implemented in the project, from material selection to garden irrigation system and waste management. The fact that the implementation of the Enerjisa Üretim Head Office project, which has LEED Gold certification, was also carried out by Diem provided convenience in this process. Currently, the Enerjisa Üretim Kozan Social Facility certification process continues.
Carrying out a project approximately 1000 km from Istanbul…
Kozan is 110 km away from Adana and approximately 1000 km away from Istanbul. Due to the fact that the project site is far from the center of Adana and is a small place, it was overcome even though there were difficulties in finding the small needs during the construction process.
Except for the concrete, steel and iron parts, most materials such as aluminum joinery, marble, parquet, lighting, ceramics, wallpaper were sent from Istanbul according to the production time and work schedule. Electric panels were made in Istanbul. Routinely checked after shipping.
Diem added a new one to its turnkey projects with Enerjisa Üretim Kozan Social Facility.
In the field of industrial facilities, the Doğadan Factory Building, Valeo and Henkel projects were completed by Diem on a turnkey basis. What is different for Diem in the Enerjisa Production project was a mixed project that included areas with unique needs such as a hotel, cafeteria, seminar hall and gym. Therefore, the variety of materials and details was much more than in other projects. Construction, finishing and landscaping works had completed by Diem on a turnkey basis.